Rounding Value (MRP 1)
Examples:
If the Rounding Value is 20, and the procurement quantity is 70, then the system will always round up the planned order to a multiple of 20.
One more example would be, if we don’t consider the Min/Max Lot size and the procurement quantity is 70, then the system would create a planned order of 80 to round off to 20 {if the Plant/Storage location stock for that material is Zero}.
Rounding Profile (MRP 1)
The static rounding value method may not satisfy all the business cases, where a given rounding value is used and the procurement proposals are rounding to that value. There may be situations where the rounding value may change according to the size of the procurement proposal; this is where the concept of rounding profile may help you.
Rounding Profile allows you to enter a procurement quantity and the corresponding rounded value that is applicable if the procurement quantities. You may configure the system to have a rounded value of 10 units, if the procurement quantity is at least 1 unit and a rounded value of 100 units, if the procurement quantity reaches 70 units. The transaction code to configure is OWD1. The Rounding profile configuration screen would look something as below. The Rounding Profile configured is named as Z001”.
Comments
Post a Comment